Construction progress in Großbothen
Germany
|
6
.
11
.
2017
News from the project development in Germany. The construction of our 750 kW solar park in Großbothen (city of Grimma, district of Leipzig) is progressing. All pile driving work was completed by the middle of calendar week 43. Civil engineering work has already begun. The first electrical work will be carried out in week 45.