Construction progress in Maulbeerwalde

Germany
|
17
.
10
.
2017

Construction progress of another solar park in Germany! The construction work for our 10 MW solar park in Maulbeerwalde (municipality Heiligengrabe, district Ostprignitz-Ruppin, Brandenburg) is progressing. The first work steps consist of the construction of the cable route connecting the plant with the Wittstock substation. The cable route has a length of approx. 9 km, of which approx. 2.5 km have already been built in cooperation with E.DIS AG. In future, 5,300 households will be supplied with solar power from the 10 MW solar plant. Commissioning of the solar park is planned for the end of the first quarter / beginning of the second quarter in 2018.