Distribution of the solar plant Maulbeerwalde has started

Germany
|
10
.
07
.
2017

The planning phase for the solar power plant in Maulbeerwalde is in its final phase. The building permit was granted to Green Energy 3000 this week. The ground-breaking ceremony is planned for the summer of this year. The construction of the plant with more than 35,000 modules will take approx. 4 weeks. It is planned to connect the 9.6 MW plant to the grid in the fourth quarter of 2017.

This project in Brandenburg will be opened to private investors. Also small investors get their chance, since participations already starting from 40 kW are made possible. Secure your tax advantages by investing in renewable energies! Take advantage of an investment reserve and special depreciation and receive income from the solar park income from the first year onwards.