Wind park Attigny: construction in final stages (France)

France
|
23
.
06
.
2023

The construction work for the Attigny wind park (Ardennes region, France) is in the final stages. In the meantime, all 4 Nordex turbines with a total capacity of 12 MWp have been erected. Test operation will start next week. The wind farm is scheduled to be commissioned at the beginning of July 2023 and will be transferred to the company's own portfolio.

Green Energy 3000 is pleased to bring another source of renewable energy to the grid in France.